Keep track of all media and communication collateral.
Tower 1 |
|
| External painting | Work in progress |
| Internal Plastering | Completed |
| Electricals | 90% completed |
| Plumbing | 75% completed |
| Aluminium window fixing | Completed |
| Tile & marble laying | 15% completed |
| False ceiling | Framing 40% completed |
Tower 2 |
|
| External & internal painting | Work in progress |
| Internal Plastering | Completed |
| Electricals | Completed |
| Plumbing | Completed |
| Aluminium window fixing | 90% Completed |
| Tile & marble laying | 90% completed |
| False ceiling | Framing completed |
| False ceiling | Boarding 80% completed |
Tower 3 |
|
| External painting | Work in progress |
| Internal Plastering | Completed |
| Aluminium window fixing | 70% Completed |
| Tile & marble laying | 40% completed |
| False ceiling | Framing 40% completed |
| False ceiling | Boarding 40% completed |
Tower 4 |
|
| External painting | Work in progress |
| Internal Plastering | Completed |
| Tile & marble laying | 70% completed |
| False ceiling | Framing completed |
| False ceiling | Boarding 65% completed |
Tower 5 |
|
| External painting | Work in progress |
| Internal Plastering | Completed |
| Electricals | 90% completed |
| Plumbing | 60% completed |
| Aluminium window fixing | 70% completed |
| Tile & marble laying | 10% completed |
| False ceiling | Framing 90% completed |
| False ceiling | Boarding 20% completed |
Tower 6 |
|
| Internal Plastering | Completed |
| Electricals | 15% completed |
| Plumbing | 15% completed |
| Aluminium window fixing | Work in progress |
Tower 7 |
|
| Internal Plastering | Completed |
| Electricals | 40% completed |
| Plumbing | 20% completed |
| Aluminium window fixing | 35% completed |
| False ceiling | Framing 70% completed |
Tower 8 |
|
| Internal Plastering | Completed |
| Electricals | 70% completed |
| Plumbing | Work in progress |
| Aluminium window fixing | 45% completed |
| False ceiling | Framing 50% completed |
OTHERS |
|
| Central Meadow | Structure complete |
| Clubhouse | Blockwork complete |
| Signature Unit Mock up | 100% completed |